Zum Inhalt wechselnExchange | Shelf repair / Shelf refurbishment |
Pro | Pro |
Requirement of the manufacturer is met | Load-bearing capacity is restored |
"Satisfaction of the warehouse operator" | serves as post protection |
visually one line | Lower costs |
the only solution for discontinued models (special designs possible) | |
considerably more cost-effective with welded frames | |
No need to uninstall cables, sprinkler systems, gratings, push-through safety devices | |
No bearing failure, as repairs/replacements are carried out during operation | |
Repair profile statically certified and DEKRA-tested | |
Contra | Contra |
High time and cost expenditure | |
Possibly long delivery times | |
Shelves must be relieved and dismantled | |
Sometimes high transportation costs | |
Generally higher capital commitment, as posts are not purchased individually | |
Need for storage |
Exchange | Repair/replacement using the example of ... |
Removing and temporarily storing goods | Store lower compartment |
Dismantling the beam | Repairing posts |
Dismantle post/frame | Store lower compartment |
Install new posts/frames | |
Installing beams | |
Store goods | |
Time required: approx. 4-6 h | Time required: approx. 0.5-1.5 h |